Data Center Commissioning and Handover Checklist
A working checklist for the electrical side of commissioning, from the plan to handover. Adapt it to your project's own commissioning plan and specification.
1. Before testing starts
โCommissioning plan agreed: levels, responsibilities, test scripts and acceptance criteria.
โLatest single-line diagrams, protection settings and sequences of operation issued to the commissioning team.
โTest access and load-bank connection points exist and are labelled.
โSafety procedures, permits and lock-out arrangements agreed.
2. Factory and delivery checks
โFAT witnessed for switchgear, UPS, generators and transformers, with records filed.
โEquipment inspected on delivery against the order and for transit damage.
โOpen FAT and delivery punch items logged with owners and dates.
3. Installation checks
โEquipment installed and labelled as drawn; torque, phase rotation and earthing checked.
โInsulation resistance and continuity tests recorded for cables and busbars.
โProtection settings loaded and verified against the coordination study.
โCable and panel schedules reconciled with what is installed.
4. Functional tests
โEach breaker, ATS and STS operated and the transfer behaviour recorded.
โUPS tested for transfer to battery, return to mains and bypass operation.
โGenerators tested on load, including start time and step load response.
โAlarms and monitoring points verified at the control system.
5. Integrated systems testing
โUtility failure with generator start and transfer, under load-bank load.
โLoss of a single component or path, to confirm the redundancy works as designed.
โCooling restart and sequencing checked through the power transition.
โResults compared against the design intent and failures re-tested after correction.
6. Handover and close-out
โAs-built drawings, test records and settings handed over.
โOperations and maintenance manuals and emergency procedures issued.
โTraining for the operations team completed and recorded.
โOutstanding items listed with owners and a closure date.
A general checklist, not a substitute for the project specification or the commissioning authority's procedures. See commissioning levels explained and FAT, SAT and IST.